SOLIDVOLTEV Charger Installation

The Solid Volt Process

What your install includes, start to finish

Every quote covers the same six stages — permits, panel work, the wire run, mounting, testing, and inspection. Here's exactly what happens at each one.

Most installs: half a day on site, permit to sign-off in about 1–2 weeks

  1. Homeowner reviewing an electrical panel photo and installation paperwork

    Site review & permit

    2–5 business days before install day

    We review the photos and video you sent, confirm your charger placement, and pull the electrical permit with your county or city. You don't have to call anyone or sign anything at city hall — it's handled, and it's included in your quote.

    What you'll see: A confirmed install date and a copy of your permit.

  2. Electrician working inside an open residential electrical panel

    Load check & panel prep

    About 1 hour on site

    A licensed electrician verifies your main breaker can carry the charger and installs its dedicated breaker. If your panel genuinely can't support it, we tell you before any work starts — no surprise charges after the fact.

    What you'll see: A new breaker labeled for your EV charger.

  3. Electrician fastening conduit to the exterior wall of a Florida home

    The wire run

    1–3 hours, depending on distance

    We run wiring from your panel to your charger spot — through the attic, along a wall in conduit, or trenched underground for a driveway pedestal. This is where most of the labor lives, and why placement drives the price.

    What you'll see: Neatly strapped conduit or a clean trench line.

    Want to know what this looks like for your house?

    Estimate my price
  4. Electrician leveling a wall connector during installation

    Mounting the connector

    About 1 hour

    Your Wall Connector goes up at the right height and side for your car's charge port, so the cable reaches without stretching across a walkway. Exterior installs get weather-rated fittings and sealant.

    What you'll see: The charger mounted, leveled, and cable hung.

  5. Electrician testing a new charger with a meter next to a plugged-in car

    Energize, test & commission

    30–45 minutes

    We energize the circuit, verify voltage and grounding, connect the charger to your Wi-Fi, and run a full load test with a vehicle before we call it done. You get walked through the app and charging settings.

    What you'll see: Your car actually charging before we leave.

  6. Finished clean charger installation with inspection tag

    Inspection & sign-off

    Typically within a week after install

    We schedule the county or city inspection and meet the inspector if needed. Once it passes, your permit is closed and the install is documented — which matters for insurance and when you sell the house.

    What you'll see: A passed inspection tag and closed permit.

Why the permit and licensed work matter

A Level 2 charger draws as much power as an electric oven, running for hours at a time. Permitted, inspected work keeps your homeowner's insurance valid, protects your warranty, and shows up as a documented upgrade when you sell. Unpermitted work can do the opposite — and it's usually the first thing a home inspector flags.

Ready to see your exact price?

The final two photos are illustrative samples of typical installs.